Kachieng Church Community Centre – Progress

The roof timbers for the Kachieng Church Community Centre were erected during July in readiness for the roof tiles which have now been purchased.

In order to ensure the building would be a completely safe construction it was decided to ask the Local Council Building Control department to visit site and carry out an inspection of the building & to make recommendations if there were any concerns.

After checking the drawings of PASH’s appointed architect against the construction to date, it was decided that the foundations & walls were to a good standard but that the roof timbers should be strengthened to ensure it can take the weight of the roof tiles & cope with any adverse weather conditions.

Additional funding required to complete the roof will be in the order of £1500.0 to £2000.00.

Church Centre

Church Centre with roof timber installed but has to be strengthened before roof tiles are fixed.